18649/24 decided approve with conditions Last updated 30/07/2025, 19:25

Application to erect additional HV transformer substations and LV switch panel enclosures, including underground power distribution, lighting, external charging units, and associated minor civil works.

Full Planning Permission

Bolton, BL3 2AW

BL3 2AW

Full Proposal

Erection of additional HV transformer sub stations and LV switch panel enclosures together with underground power distribution, lighting, external charging units and associated minor civils

Application Timeline

Application Registered
19/07/2024
Application Validated
04/09/2024
Target Decision Date
30/10/2024
Committee Date
N/A
Decision Made
21/01/2025
Decision Issued
21/01/2025

Case Officer

Applicant

Mr Paul Groves